Inspecting a Deck, Illustrated
By Nick Gromicko, Founder, International Association
of Certified Home Inspectors (InterNACHI) Graphics by InterNACHI's
Lisaira Vega
More than 2 million decks are built and replaced each year in North America. InterNACHI estimates that of the 45 million existing decks, only 40% are completely safe.
Because decks appear to be simple to build, many people do not realize that decks are, in fact, structures that need
to be designed to adequately resist certain stresses. Like any other house or building, a deck must be designed to support
the weight of people, snow loads, and objects. A deck must be able to resist lateral and uplift loads that can act on
the deck as a result of wind or seismic activity. Deck stairs must be safe and handrails graspable. And, finally,
deck rails should be safe for children by having proper infill spacing.
A deck
failure is any failure of a deck that could lead to injury, including rail failure, or total deck collapse. There is
no international system that tracks deck failures, and each is treated as an isolated event, rather than a systemic problem.
Very few municipalities perform investigations into the cause of the failure, and the media are generally more concerned with
injuries rather than on the causes of collapses. Rail failure occurs much more frequently than total deck collapses;
however, because rail failures are less dramatic than total collapses and normally don't result in death, injuries from rail
failures are rarely reported. Here are some interesting facts about deck failure:
- More decks collapse in the summer than in the rest
of the year combined.
- Almost every deck collapse occurred while the decks were occupied or under a heavy
snow load.
- There is no correlation between deck failure and whether the deck was built with or without a building
permit.
- There is no correlation between deck failure and whether the deck was built by a homeowner or a
professional contractor.
- There is a slight correlation between deck failure and the age of the deck.
- About 90% of deck collapses occurred as a result of the separation of the house and the deck ledger board, allowing
the deck to swing away from the house. It is very rare for deck floor joists to break mid-span.
- Many more
injuries are the result of rail failure, rather than complete deck collapse.
- Deck stairs are notorious
for lacking graspable handrails.
- Many do-it-yourself homeowners, and even contractors, don't believe
that rail infill spacing codes apply to decks.
This
document does not address specific building codes, balconies, lumber species, grade marks, decks made of plastics or composites,
mold, or wood-destroying insects.
This document
focuses on single-level residential and commercial wood decks. Recommendations found within this document exceed the
requirements of both InterNACHI's Residential Standards of Practice and the International Standards of Practice for Inspecting
Commercial Properties.
A
proper deck inspection relies heavily on the professional judgments of the inspector. This document will help improve
the accuracy of those judgments. Deck Inspection Tools:
- flashlight
- measuring tape
- ladder
- level
- plumb bob
- probing tool
- hammer
Optional Inspection Tools:
- moisture meter
- magnet
- calculator
Deck Loads:
A deck inspection should progress
in much the same order as deck construction. Inspectors should start at the bottom. If a deck is deemed unsafe
from underneath, the inspector should not walk out onto the deck to inspect decking, handrails, etc. The inspector should
stop and report the safety issues.
The
image above depicts an evenly distributed deck load. Building codes require decks to be designed to carry a uniformly
distributed load over the entire deck. If evenly distributed, half of the load is carried by the deck-to-house connection,
and the other half is carried by the posts.
The
image above depicts a likely deck load distribution. People tend to gather near the railings of a deck, and so more
load is likely carried by the posts.
Hot tubs filled with water and people are heavy and can weigh
a couple of tons. Most decks are designed for loads of 40 to 60 per square foot. Hot tubs require framing that
can support over 100 per square foot.
Footings and Posts:
Required footing
depths vary based on local building codes. The depth is normally below the frost line, or 12 inches (where frost lines
are not applicable).
The
above image depicts the 7-Foot Rule. On steep properties, the slope of the ground around the footing could
affect the footing's stability. The 7-Foot Rule states that there should be a least 7 feet between the
bottom of a footing and daylight.
Posts in contact with soil should be pressure-treated and oriented
so the cut end is above grade.
The
image above depicts a free-standing deck (not attached to the home or building). A footing near a home may not be on
undisturbed soil. Some codes consider soil to be "undisturbed" if it hasn't been disturbed in more than five
years. It may be difficult to find undisturbed soil near the foundation of a new home.
The
image above depicts a post base that is not attached to its footing. Posts should be connected to their footings so
that the posts don't lift or slip off.
The
image above depicts a pre-cast concrete pier. Posts can lift out of pre-cast concrete piers, and piers can slide.
Posts should be connected to their footings so that the posts don't lift or slip off.
The
image above depicts a proper post-to-footing connection. Posts should be connected to their footings so that the posts
don't lift or slip off their footings.
The
image above depicts an adjustable post-to-footing connection. Posts should be connected to their footings so that the
posts don't lift or slip off their footings.
The
above image depicts a lawn sprinkler keeping a deck post wet. Lawn sprinkler systems that regularly keep the deck wet
contribute to decay.
The
image above depicts a downspout contributing to post decay. Downspouts should not discharge near deck posts.
The
image above depicts the indentation left over from the footing hole, causing a puddle. Puddles contribute to post decay.
Wood can decay and degrade over time with exposure to the elements. Decay is a problem that worsens with time.
Members within the deck frame that have decayed may no longer be able to perform the function for which they were installed.
Paint can hide decay from an inspector and so should be noted in the report.
The
image above depicts a pick test. The "pick test" uses an ice-pick, awl or screwdriver to penetrate the wood
surface. After penetrating the wood, the tool is leveraged to pry up a splinter, parallel to the grain, away from the
surface. The appearance and sound of the action is used to detect decay. The inspector should first try the pick
test in an area where the wood is known to be sound to determine a "control" for the rest of the inspection.
Decayed wood will break directly over the tool with very few splinters, and less or almost no audible noise compared to sound
wood. The pick test cannot detect decay far from the surface of the wood.
The
image above depicts a pick test on a deck post. Although deck inspections are visual-only inspections, inspectors may
want to dig down around posts and perform pick tests just below grade level to look for decay.
The
image above depicts a high deck being supported with 4'x 4' posts. Tall 4'x 4' posts twist under load and 4'x
4' posts, even when treated, decay below grade too quickly. Deck posts should be at least 6'x 6', and be no higher
than 12 feet; 14 feet is acceptable if cross-bracing is used.
Girders and Beams:
The
image above depicts the minimum distance of untreated support members from grade. Untreated joists should be at least
18 inches away from the ground. Girders should be 12 inches away from the ground. However, in many situations,
exceptions are made where the elevation of the home does not provide for these minimum distances and the climate is very dry.
The
image above depicts a girder improperly relying on the sheer strength of lag bolts. Girders should bear directly on
posts.
The image
above depicts a girder properly resting on a notched post. Girders should bear directly on posts.
The
image above depicts a girder properly resting on a post. Girders should bear directly on posts.
The image above depicts a butt joint improperly
located within a girder span. Butt joints in a girder span are not permitted. Butt joints must be located
above posts.
The image above depicts notches in a supporting beam. Notches must be less than one-quarter the depth of
the member. On the tension and compression faces, the notch depth must be less than one-sixth of the member's
depth, and the notch length must be less than one-third of the member's depth. Notches are not permitted in
the middle third of spans, or on the tension face of members that are greater than 3½ inches thick.
The image above depicts a level being used to check for beam sag. Even with a carpenter's
level, it can be difficult to see beam sag from the front.
The image above depicts beam sag being eyed-up. Often it is easier to detect beam sag by
eye than with a level by looking along the bottom edge of the beam.
Ledger Connection:
The most
common causes of deck collapse are ledgers that pull away from the band joists of homes and buildings.
The two most common ways to correctly attach a ledger to a structure are with lag screws or through-bolts.
The installation of through-bolts requires access to the back-side of the rim joist which, in some cases, is not possible
without significant removal of drywall within the structure.
Most building codes state that,
where positive connections to the primary building structure cannot be verified during inspection, decks shall be self-supporting
(free-standing).
Determining the exact required spacing for the ledger fasteners is based on many
factors, including:
- joist
length
- type of fastener
- diameter of fastener
- sheathing thickness
- use of stacked washers
- type of wood species
- moisture content
- band joist integrity
- deck loads
...and
so is beyond the scope of a visual inspection. However, the number of ledger fasteners required is primarily determined
by the length of the joists. InterNACHI's ledger fastener spacing formula provides inspectors with a rule-of-thumb:
On-center spacing of ledger fasteners in inches
= 100 ÷ joist length in feet.
A deck with substantially fewer ledger fasteners than that recommended by InterNACHI's
formula may be unsafe.
The
image above shows the minimum distance of fasteners to the edges and ends of a ledger board. Lag screws or bolts should
be staggered vertically, placed at least 2 inches from the bottom or top, and 5 inches from the ends of the ledger
board.
Through-bolts should be a minimum of ½-inch in diameter, and have washers
at the bolt head and nut. Lag screws should also be a minimum of ½-inch in diameter and have washers. Expansion
and adhesive anchors should also have washers.
Deck ledgers should be of at least 2'x 8' pressure-treated
wood.
Ledger Board and Band Joist Contact:
The
image above depicts washers being used as spacers between the ledger board and band joist, which is incorrect.
In some cases, the ledger board and band joist are intentionally kept separated by a stack of washers on the lag screw
or bolts to allow water to run between the two boards. In other cases, there is insulation between the two boards.
Even worse is when the siding or exterior finish system was not removed prior to the installation of the ledger board.
Situations like this, where the ledger board and band joist are not in direct contact, significantly reduce the strength of
the ledger connection to the structure and are not recommended by InterNACHI, unless the two members are sandwiching structural
sheathing.
The
image above depicts a ledger board and band joist sandwiching the structural sheathing (correct).
All through-bolts should have washers at the bolt head
and nut.
The
image above depicts a hold-down tension device. The 2007 IRC Supplement requires hold-down tension devices at
no less than two locations per deck.
Codes in some areas outright forbid attaching a ledger board to
an open-web floor truss.
The
image above depicts a ledger board attached to a concrete wall. Caulking rather than flashing is used.
The
image above depicts a ledger board attached to hollow masonry. When the ledger is attached to a hollow
masonry wall, the cell should be grouted.
The
image above depicts a ledger board attached to brick veneer. Ledger boards should not be attached to brick veneer.
The
image above depicts both over and under ledger board flashing. The ledger board should always be flashed even when the
home or building has a protective roof overhang.
Aluminum flashing is commonly
available but should not be used. Contact with pressure-treated wood or galvanized fasteners can lead to rapid corrosion
of aluminum.
The
image above depicts a deck ledger attached to an overhang. Decks should not be attached to overhangs.
The
image above depicts proper framing around chimneys or bay windows that are up to 6 feet wide. Framing around chimneys
or bay windows that are more than 6 feet wide require additional posts.
The
image above depicts a cantilevered deck. Joists should be cantilevered no more than one-quarter of the joist
length or three times the joist width (nominal depth), whichever is smaller.
The
image above depicts a joist cantilever in the front of the deck and girder cantilevers on both sides of deck posts.
Joists should be cantilevered no more than one-quarter the joist length or three times the joist width (nominal
depth), whichever is smaller. Girders can be cantilevered over their posts no more than on-quarter the girder length.
There are three ways a joist can be attached to a ledger:
The
first is by resting the joist on a ledger strip. The image above depicts a joist properly resting on a 2"x 2"
ledger strip.
The
second is by notching over a ledger strip. The image above depicts a notched joist properly resting a 2"x 2"
ledger strip.
The
third is by hanging the joists with joist hangers. The image above depicts joists properly attached to a ledger by way
of metal joist hangers.
The
image above depicts a joist cut too short. Joists may rest on 2"x 2" ledgers like the one above (or in joist
hangers), but joists must be cut long enough to reach the ledger or band joist that is supporting them.
The
image above depicts joists that are not fully resting in their joist hangers. Joists should be fully resting in their
joist hangers.
Bracing:
The
image above depicts a deck with post-to-joist diagonal bracing. Decks greater than 8 feet above grade should have
diagonal bracing from posts to girder and from posts to joists.
The
image above depicts a deck with post-to-girder diagonal bracing. Decks greater than 8 feet above grade should have
diagonal bracing from posts to girder and from posts to joists.
Free-standing decks (not supported by the home or building) should have diagonal
bracing on all sides.
The
image above depicts underside diagonal bracing of a deck. Decks greater than 3 feet above grade that do not have diagonal
decking should have diagonal bracing across the bottoms of the joists to keep the deck square. A deck that is not held
square could permit the outer posts to lean to the right or left, parallel to the ledger board, and thus twist the ledger
away from the home or building.
Cracks:
As wood ages, it is common
for cracks to develop. Large cracks (longer than the depth of the member) or excessive cracking overall can weaken deck framing.
Toe-nailed connections are always at risk for splitting. Splitting of lumber near connections should be noted by the
inspector.
Connectors and Fasteners:
The inspector should note
missing connectors or fasteners. All lag screws and bolts should have washers.
The
image above depicts a hammer test. Depending on how the deck was built, vital connections may have degraded over time
due to various factors. Issues such as wobbly railings, loose stairs, and ledgers that appear to be pulling away from
the adjacent structure are all causes for concern. The tightness of fasteners should be checked. If it is not
possible to reach both sides of a bolt, it may be struck with a hammer. The ring will sound hollow with vibration if the fastener
is loose. The ring will sound solid if the connection is tight. The hammer test is subjective, so the inspector
should hammer-test bolts that can be confirmed as tight or loose, and compare the sounds of the rings to develop
a control.
Corrosion of Connectors and Fasteners:
All screws,
bolts and nails should be hot-dipped galvanized, stainless steel, silicon bronze, copper, zinc-coated or corrosion-resistant.
Metal connectors and fasteners can corrode over time, especially if a product with insufficient corrosion-resistance was originally
installed. Corrosion of a fastener affects both the fastener and the wood. As the fastener corrodes, it causes the wood
around it to deteriorate. As the fastener becomes smaller, the void around it becomes larger. Inspectors normally
do not remove fasteners to check their quality or size, but if the inspector removes a fastener, s/he should make sure
that removal doesn't result in a safety issue. Fasteners removed should be from areas that have the greatest exposure
to weather. Some inspectors carry new fasteners to replace ones they remove at the inspection.
Posts and
Rails:
The
image above shows a guardrail supported solely by balusters. Guardrails should be supported by posts every 6 feet.
The
image above depicts a notched-deck guardrail post attachment. This common notched-type of attachment is permitted by
most codes, but could become unsafe, especially as the deck ages. Because of leverage, a 200-pound force pushing the
deck's guardrail outward causes a 1,700-pound force at the upper bolt attaching the post. It is difficult to attach
deck guardrail posts in a manner that is strong enough without using deck guardrail post brackets.
The
image above depicts a notched-deck guardrail post attachment. This notched-around-decking-type of attachment is permitted
by most codes, but could become unsafe, especially as the deck ages. Because of leverage, a 200-pound force pushing
the deck's guardrail outward causes a 1,700-pound force at the upper bolt attaching the post. It is difficult to attach
deck guardrail posts in a manner that is strong enough without using deck guardrail post brackets.
The
image above depicts a deck guardrail post properly attached with brackets. Because of leverage, a 200-pound force pushing
the deck's guardrail outward causes a 1,700-pound force at the upper bolt attaching the post. It is difficult to attach
deck guardrail posts in a manner that is strong enough without using deck guardrail post brackets.
The
image above depicts a post and balusters cut level and not shedding water. The end-grain of vertical posts and balusters
should not be cut level.
The
image above depicts a post and balusters properly cut at angles to shed water. The end-grain of vertical posts and balusters
should be cut at an angle.
Missing Guardrails:
Decks that
are greater than 12 inches above adjacent areas should have guardrails around the edges. Some codes require guardrails
only around the edges of decks 30 inches or higher.
Improper Guardrail Height:
Most residential
codes require the top of the guardrail to be at least 36 inches from the deck surface. Most commercial code height is
42 inches.
The
image above depicts child-unsafe guardrail infill. Infill should not permit a 4-inch sphere to pass through.
The
image above depicts horizontal balustrades. Ladder-type guardrail infill on high decks is prohibited by some local
codes because they are easy for children to climb over.
Decking:
The
image above depicts deck framing near a chimney or bay window. The ends of decking boards near the chimney or bay window
can extend unsupported up to 6 inches.
The above image depicts decking that is
laid too tight. Decking should have 1/8-inch gaps between boards so that puddles don't form.
The
above image depicts decking that is properly spaced. Decking should have 1/8-inch gaps between boards so that puddles
don't form.
The
image above depicts decking that isn't staggered properly. Decking should be staggered so that butt joints don't land
on the same joist side by side.
The
image above depicts decking lengths. Some are too short. Each segment of decking should bear on a minimum of four
joists.
Decking Nail Pull-Out:
Inspectors should look for splitting
in decking and nail pull-out. Aside from the structural issue, nails that have pulled out or screws that are not driven
into the decking fully can cause injury to bare feet.
Stairs:
The
image above depicts a deck stair stringer. Stair stringers shall be made of 2"x 12" lumber at a minimum, with
no less than 5 inches wide at any point.
The
image above depicts deck stair stringers. Stringers should be no more than 36 inches apart.
The
image above depicts ledger strips properly located under stair treads. Where solid stringers are used, stair treads
should be supported with ledger strips (as depicted), mortised, or supported with metal brackets.

The
image above depicts a set of stairs with open risers. Most deck stairs have open risers and are not safe for children.
Risers may be open but should not allow the passage of a 4-inch diameter sphere.

The image above depicts stair riser height.
To minimize tripping, the maximum variation amongst riser heights (difference between the tallest and shortest risers) should
be no more than 3/8-inch. Deck Lighting:
Decks rarely have light sources that
cover the entire stairways. Any unlit stairway is a safety issue. Stair Handrails:
Stairs
with four or more risers should have a handrail on at least one side. According to the International Standards
of Practice for Inspecting Commercial Properties, ramps longer than 6 feet should have handrails on both sides.

The
image above depicts proper stair handrail height. Handrail height should be between 34 and 38 inches measured vertically
from the sloped plane adjoining the tread nosing.

The
image above depicts a stair handrail that is not graspable. Many deck handrails improperly consist of 2"x 6"
lumber or decking. Handrails should be graspable, continuous and smooth.
The next
three images depict graspable handrails:

The
three images directly above depict graspable handrails. Many deck handrails improperly consist of 2"x 6" lumber
or decking. Handrails should be graspable, continuous and smooth.

The
image above depicts the minimum distance between stair handrail posts. Stair handrails should have posts at least every
5 feet.

The
three images directly above depict graspable handrails. Many deck handrails improperly consist of 2"x 6" lumber
or decking. Handrails should be graspable, continuous and smooth.


The
image above depicts permitted spacing at stairs. Larger spacing presents a child-safety issue.
Electrical
Receptacle:

The
image above depicts a deck with an electrical receptacle, but the receptacle does not have a weatherproof cover. As
of 2008, the National Electric Code requires at least one receptacle outlet on decks that are 20 square foot or larger.

The
image above depicts a weatherproof receptacle cover. The deck receptacle should have a weatherproof cover.
Deck Location:

The
image above depicts a deck located above a septic tank access. Decks should not be located where they might obstruct
septic tank accesses, underground fuel storage tanks, well heads, or buried power lines.

The
image above depicts a deck obstructing a basement bedroom's emergency egress window. Egress openings under decks and
porches are acceptable, provided the escape path is at least 36 inches (914 mm) in height, and the path of egress is
not obstructed by infill or lattice.

All content copyright © 2006-2009 the International Association
of Certified Home Inspectors, Inc.